The Challenge

Weymouth, Massachusetts was expanding its water treatment facility and discontinuing the use of alum sludge containment ponds. As part of this transition, the town needed a reliable solution for alum sludge removal and sediment extraction from the reservoir previously used for decanting sludge from the containment ponds.

The Solution

The town hired a consulting engineer who pilot-tested Geotube® dewatering containers. With proper chemical conditioning, this technology was shown to provide the most cost-effective volume reduction for alum sludge. Following the pilot’s success, the awarded contractor installed a laydown area using crushed stone and a textile underlayment mat, designed with drainage elevations of 1% leading to collection sumps. Geotube® containers were then installed with interconnecting pipe manifolds to distribute flow efficiently across multiple units.

Alum sludge and sediment were pumped using long-reach excavators modified with hydraulic pumps and a floating hydraulic dredge, which enabled access to hard-to-reach areas of the reservoir and former containment ponds.

geotube

Flow rates ranged from 800-2,500 gpm, with slurry solids content of 1-6% containing debris such as rocks, sticks, and leaves. The slurry was chemically treated using SmartFeed™ technology* to maintain optimal polymer dosing and ensure daily performance monitoring. The result was high water capture efficiency with discharge quality measuring just 24 NTUs. After several weeks of drainage, dewatered cake solids reached 38% dry solids, confirming the effectiveness of the alum sludge removal process.

* SmartFeed™ is a patent pending technology of Underwater Mineral Processing Services (UMPS).

Customer Feedback: A Proven Solution for Alum Sludge Removal

“As a contractor dealing with the town’s consultant on project timelines, I found the daily process benchmarking provided by the SmartFeed™ chemical conditioning system, with onsite support of the filtration manager, was invaluable in making weekly project optimization decisions.”

This successful alum sludge removal at Weymouth’s treatment facility was made possible through the combined efforts of Underwater Mineral Processing Services (UMPS), Environmental Partners, D&C Construction, and Aries Chemical. By integrating Geotube® and SmartFeed™ technology, the team delivered a highly effective and environmentally responsible solution.

* SmartFeed™ is a patent pending technology of Underwater Mineral Processing Services (UMPS).

Leverage Our Alum Sludge Removal Expertise

The Weymouth reservoir restoration project demonstrates the effectiveness of combining technologies for municipal slum sludge removal. The results delivered high dewatering efficiency and offered a cost-effective approach to streamlined sludge management.

Contact us today to learn how our sludge dewatering solutions can support your industrial water treatment needs.

Questions?
Contact James E. Meagher
207-741-2955
207-751-4416 (cell)
860-767-8256 x. 136 (office)
[email protected]